Bradley Group was contracted to carry out the demolition of the former Shadsworth Leisure Centre. The scope of the Shadsworth Leisure Centre Demolition Project included mechanical demolition of the buildings, asbestos removal, infilling of voids, disconnection of services, external works, protection of sub stations and party wall works.
Extensive Asbestos Removal
Due to the facility’s closure several years prior and the increasing risk of vandalism, Bradley Group was tasked with overseeing the demolition and extensive asbestos removal at the site, including the adjoining swimming pool area. Acting as the Principal Contractor, Bradley Group also coordinated and managed subcontractors who handled the M&E (Mechanical and Electrical) strip-out within the building before demolition began.
Party Wall Requirements
The project required meticulous management, particularly due to the proximity of a live building connected to the leisure centre and the need to meet party wall requirements. Additionally, the site was bordered by existing roads, pavements, and adjacent occupied buildings, all of which required comprehensive traffic management protocols.
Effective Noise Management
Given the presence of adjacent live areas, effective noise management was a critical component of the project. To mitigate noise during the demolition and crushing phases, Bradley Group implemented additional sound barrier curtains at key areas as requested by the client.
Bradley Group also facilitated visits from structural engineers and supported investigation work throughout the project.
Ground Processing and Infilling Voids
Once the asbestos removal and demolition phases were completed, the team proceeded with ground processing and the infilling of the pool voids.
UK Safety Regulation Compliance
The entire project was executed in full compliance with UK safety regulations, highlighting Bradley Group’s dedication to maintaining the highest standards in both environmental management and construction practices.
I worked with Bradley Group on the recently completed Shadsworth Leisure Centre demolition project on behalf of Blackburn with Darwen Council.
From the outset Bradley showcased their capabilities and knowledge of the asbestos removal and demolition activities, this was reflected within the site documentation and also by witnessing live onsite duties. I completed several site audits and attended progress meetings, Bradley’s on site safety procedures and set up were of the highest standard and quality was maintained throughout the project.
Bradley reacted quickly and efficiently with scope changes and ensured both myself and the client were kept up to date.
Overall great work from the Bradley team as whole and I have no reservations about working with them again in the future.
Joe Readfern, Director at CRE8 Chartered Surveyors & Building Consultancy
I worked with Bradley Demolition on a scheme commencing July 2024 and completing in November 2024. The scheme was the demolition of the former Shadsworth Leisure Centre, Shadsworth Rd, Blackburn, BB1 2HT comprising of pulling down of main buildings, grubbing-up of foundations and disused services, removal of extensive amounts of asbestos, filling of voids with compacted crushed fill and protection.
The works included liaison with the adjacent adjoining occupied property and for working around the adjacent distribution substation which was to be retained in its current position post demolition with services retained to supply the adjacent former school building. There was a significant amount of asbestos that needed to be removed and Bradleys in house asbestos team managed the removal of this efficiently and in a very safe manner.
The scope of works altered during the course of the demolition meaning that only two thirds of the building could be demolished and Bradley Demolition adapted to this very well and were able to advise us with their expertise. Bradley Demolition also managed a nominated mechanical / electrical contractor on this scheme. I have found Bradley Demolition to be an extremely reliable and knowledgeable Contractor. I can confirm that this scheme was carried out on programme and within budget.
The standard of workmanship is outstanding and the operative’s performance on site and site management is exemplary. Health and safety is exceptional and risk assessments, method statements and health and safety documentation is received in advance of any works commencing on site. I would not hesitate in using this Contractor again.
Wendy Penman, Senior Building Surveyor, Blackburn & Darwen Borough Council